Schedule Change for Cedar- Capital Project in the Home Starting November 4th, 2024

During the week of November 4th – November 10th, the hallway carpeting in the Oak and Cedar home areas will be removed and replaced with luxury vinyl plank flooring.

To allow full access to the flooring and for the safety of our residents and staff, we will need to vacate a section of the home area each day from 8:am to 5:00 pm.

The following schedule will be followed:

Oak Ridge

November 4th: Rooms: 101-114

November 5th: Rooms: 115, 117, 119, 121, 123, 125, the tub room, activities (no baths during the day- alternative arrangements will be made by the nursing team to ensure residents receive their baths)

November 6th: Rooms: 126, 128 – 138

Please note the schedule change below:

Cedar Hills

November 7th: Rooms 201-208, 211, 213, 215, 217, the tub room.

November 8th: Rooms 219-227, 229, activities.

November 9th: Rooms 228, 230–238, lounge

** This schedule will be subject to change depending on the installer's progress during the week. **

Additional staff will be present to assist in redirecting residents during the day. Should something be needed from within a vacated room, please ask the installers if access can be granted.

Please contact Steve Files, at steve.files@muskoka.on.ca or ext. 4804, if you have any questions regarding this project.

Share Schedule Change for Cedar- Capital Project in the Home Starting November 4th, 2024 on Facebook Share Schedule Change for Cedar- Capital Project in the Home Starting November 4th, 2024 on Twitter Share Schedule Change for Cedar- Capital Project in the Home Starting November 4th, 2024 on Linkedin Email Schedule Change for Cedar- Capital Project in the Home Starting November 4th, 2024 link